Brief Description of the Work undertaken by BEC Group
Civil, Mechanical, Electrical & Instrumentation construction works.
Salient Features
Survey and setting out of equipment / pipe rack foundations, excavation/back-filling, substation building, concreting works (3,500 M3 of Concrete) for equipment / pipe rack, fireproofing, etc.
Fabrication, erection, hydrotest, flushing and re-instatement of Piping (52.6 kilometers) in carbon steel and stainless steel (½ inch dia to 24 inch dia) with 100,000 inch dia of Welding.
Fabrication and erection of Structural Steel (650 tons)
Heavy Lift operation of 725 tons (Heaviest Lift: 106.9 tons, Highest Lift: 56 metres)
Erection, cleaning, final inspection and box-up of 135 Equipments (including 35 Heat Exchangers, 2 Pumps, 6 Fin Fan Coolers, 3 Compressors, 1 Fired Heater, 4 Reactors, 4 Columns, 2 Tanks, etc).
Electrical cable tray works, cable pulling (41 kilometers), installation of transformers and panels, earthing, lighting all associated electrical works including inspection and testing.
Instrumentation cable tray works, cable pulling (72 kilometers), conduit works, fabrication / installation of ducts and supports, calibration of tagged items, air piping. Instrumentation works including inspection and testing.