SALALAH METHANOL PLANT

Client :
Salalah Methanol Company
Location:
Oman
Sector:
Industrial
Services:
Civil Construction , Oil, Gas & Power ,
Project Partner :
GS Engineering & Construction

 

Brief Description of the Work undertaken by BEC Group

Civil, Mechanical, Equipment Installation and Piping Works for Salalah Methanol Project Process Train.

 

Project Highlights - Process Area

Civil Foundation –storage tanks, pipe racks, equipments Reformer 768 nos tubes, Heavy Ends Column: 60 Mtr (Tallest Equipment, weight 470 Ton), Methanol Convertor: 493 Ton (Heaviest Equipment, height 20 M), Equipment internals of columns & drums, Sygas compressor condensing unit, Syngas Compressor, Lube oil unit, Pumps - 42 nos, Air coolers- 60 nos, Pipe fabrication and erection (0.5” - 52”, Thk 3.91 - 36.4 mm).