Brief Description of the Work undertaken by BEC Group
The scope of work includes design, engineering, manufacture, inspection, shop testing, delivery, transportation and storage at site, erection, testing, commissioning, and handing over upgraded system to the Client. Scope includes complete civil works including design, supply and installation. Demolition of some of the existing plant and handing over to OETC specified stores also forms part of the scope which consisting of:
- 132kV GIS
- 125MVA Transformers
- 33kV GIS
Salient Features:
- Construction of New 33kV Building and associated Civil Works
- Foundations for 125MVA Transformer foundation
- Construction of Fire Pump House
- Building MEP Services including HVAC
- Fuji Electrical Make 132kV Gas Insulated Switchgear (GIS) – 2 Bays
- 132/33kV 125MVA Transformer – 1 Nos
- 315kVA, 33/0.415kV Earthing Auxiliary Transformer
- Neutral Earthing Resistor (National Sw.Gear, India)
- 33kV Gas Insulated Switchgear (Siemens, Germany) - 26 bays
- 33kV, 20MVAr Capacitor Banks – 2 Sets (System Power, UK)
- Control & Relay Panels for 132kV & 33kV System (ETA-PCS, UAE)
- LVAC Panels (ETA-PCS, UAE)
- 110V DC System (HBL, India)
- Scada & RTU System (ABB)